Norton: grid connection queue
Norton GSP · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
2 projects with 280 MW are waiting to connect here (largest by capacity: solar, solar + storage). Contracted dates run from 31 Oct 2031 to 30 Oct 2035.
2projects in the queue
280 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Norton Solar Farm | RWE Renewables UK Solar and Storage Limited | Solar | 180 | 31 Oct 2031 | Medium | 31 Oct 2031 | Scoping | none |
| Hill House Farm Solar and Storage | BSR APPLICATIONS LIMITED | Solar + storage | 100 | 30 Oct 2035 | Low | 30 Oct 2035 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Norton?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Norton East 400kV: 1,630 MW waiting
- Norton 400kV: 275 MW waiting
- Norton 275kV: 98 MW waiting
- Teeside Connection Node A 400kV: 1,240 MW waiting
- Spennymoor 400kV: 850 MW waiting