Norton 275kV: grid connection queue
Norton 275kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
2 projects with 98 MW are waiting to connect here (largest by capacity: battery storage, solar + storage). Contracted dates run from 31 Oct 2027 to 1 Jun 2029.
2projects in the queue
98 MWwaiting to connect
0 MWalready connected
41 MWholding Gate 2
0date moves since 2 Jun 2026
41 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Norton PV and BESS | Darlington Solar 1 Limited | Solar + storage | 41 | 31 Oct 2027 | High | 30 Oct 2029 | Consents Approved | 2 |
| Norton | BAYWA R.E. UK LIMITED | Battery storage | 57 | 1 Jun 2029 | Medium | 1 Jun 2029 | Awaiting Consents | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Norton 275kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Norton East 400kV: 1,630 MW waiting
- Norton: 280 MW waiting
- Norton 400kV: 275 MW waiting
- Teeside Connection Node A 400kV: 1,240 MW waiting
- Spennymoor 400kV: 850 MW waiting