Ayrshire Grid 400kV: grid connection queue

Ayrshire Grid 400kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 200 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 17 Mar 2028 to 17 Mar 2028.

1project in the queue
200 MWwaiting to connect
0 MWalready connected
200 MWholding Gate 2
1date moves since 2 Jun 2026
200 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Hunterston Energy Storage FacilityHUNTERSTON GRID 1 LTDBattery storage20017 Mar 2028High17 Mar 2030Consents Approved2

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
9 Jun 2026Hunterston Energy Storage Facility27 Aug 202517 Mar 2028+31 months

Thinking of connecting near Ayrshire Grid 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.