Coryton South 400kV: grid connection queue

Coryton South 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

1 project with 1,000 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 30 Jun 2029 to 30 Jun 2029.

1project in the queue
1,000 MWwaiting to connect
800 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Gateway Energy Centre Power StationGATEWAY ENERGY CENTRE LIMITEDBattery storage1,00030 Jun 2029Medium30 Jun 2029Consents Approvednone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Coryton Grid 33kVUK Power Networks0.7 km1.1 MW38 MW
Shell Grid 33kVUK Power Networks3.7 km3.5 MW35 MW
Rainbow Ln Primary 11kVUK Power Networks4.2 km3.5 MW2.8 MW
Canvey Primary 11kVUK Power Networks4.9 km22 MW7.9 MW
South Benfleet Grid 33kVUK Power Networks5.5 km73 MW21 MW
South Benfleet Primary 11kVUK Power Networks5.5 km35 MW21 MW

Thinking of connecting near Coryton South 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points