Kingsnorth 132kV: grid connection queue

Kingsnorth 132kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

2 projects with 180 MW are waiting to connect here (largest by capacity: solar + storage, mixed and other). Contracted dates run from 22 Sep 2028 to 31 Oct 2028.

2projects in the queue
180 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
180 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Rochester Renewable ProjectVATTENFALL WIND POWER LTDMixed and other6022 Sep 2028High7 May 2031Scopingnone
KingsnorthENSO GREEN HOLDINGS G LIMITEDSolar + storage12031 Oct 2028High31 Oct 2030Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Halling 11kVUK Power Networks2.6 km20 MW12 MW
Medway Grid 33kVUK Power Networks3.0 km121 MW35 MW
Medway 11kVUK Power Networks3.0 km24 MW6.4 MW
Strood 11kVUK Power Networks3.2 km93 MW16 MW
Chatham Grid 33kVUK Power Networks3.2 km121 MW43 MW
Cobham Kent 11kVUK Power Networks4.6 km14 MW3 MW

Thinking of connecting near Kingsnorth 132kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.