Kingsnorth 400kV: grid connection queue
Kingsnorth 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
4 projects with 2,850 MW are waiting to connect here (largest by capacity: mixed and other, battery storage). Contracted dates run from 31 May 2023 to 30 Apr 2032.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Cuxton 49.5MW BESS | Cuxton Energy Storage Limited | Battery storage | 50 | 31 May 2023 | n/a | Consents Approved | none | |
| Damhead Creek 2 | VPI Power Limited | Mixed and other | 1,800 | 31 Oct 2030 | Medium | 31 Oct 2030 | Consents Approved | none |
| Kingsnorth BESS NP | NORIKER POWER LTD | Battery storage | 500 | 31 Dec 2030 | Medium | 31 Dec 2030 | Scoping | 1 |
| Medway 3 Power Station | MEDWAY POWER LIMITED | Mixed and other | 500 | 30 Apr 2032 | Low | 30 Apr 2032 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 3 times: 2 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 13 Oct 2026 | Kingsnorth BESS NP | 29 Oct 2032 | 31 Dec 2030 | -22 months |
| 13 Oct 2026 | Medway 3 Power Station | 31 Dec 2030 | 30 Apr 2032 | +16 months |
| 21 Jul 2026 | Damhead Creek 2 | 31 Aug 2025 | 31 Oct 2030 | +62 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Halling 11kV | UK Power Networks | 2.6 km | 20 MW | 12 MW |
| Medway Grid 33kV | UK Power Networks | 3.0 km | 121 MW | 35 MW |
| Medway 11kV | UK Power Networks | 3.0 km | 24 MW | 6.4 MW |
| Strood 11kV | UK Power Networks | 3.2 km | 93 MW | 16 MW |
| Chatham Grid 33kV | UK Power Networks | 3.2 km | 121 MW | 43 MW |
| Cobham Kent 11kV | UK Power Networks | 4.6 km | 14 MW | 3 MW |
Thinking of connecting near Kingsnorth 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- KINGSNORTH B 400KV SUBSTATION: 400 MW waiting
- Kingsnorth 132kV: 180 MW waiting
- NorthFleet 400kV: 300 MW waiting
- North Kent Connection Node C 400kV: 532 MW waiting
- Coryton South 400kV: 1,000 MW waiting