KINGSNORTH B 400KV SUBSTATION: grid connection queue
KINGSNORTH B 400KV SUBSTATION · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 400 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 29 Oct 2032 to 29 Oct 2032.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Kingsnorth Power Station | QE KINGSNORTH SPV LIMITED | Solar + storage | 400 | 29 Oct 2032 | Low | 29 Oct 2032 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Halling 11kV | UK Power Networks | 2.6 km | 20 MW | 12 MW |
| Medway Grid 33kV | UK Power Networks | 3.0 km | 121 MW | 35 MW |
| Medway 11kV | UK Power Networks | 3.0 km | 24 MW | 6.4 MW |
| Strood 11kV | UK Power Networks | 3.2 km | 93 MW | 16 MW |
| Chatham Grid 33kV | UK Power Networks | 3.2 km | 121 MW | 43 MW |
| Cobham Kent 11kV | UK Power Networks | 4.6 km | 14 MW | 3 MW |
Thinking of connecting near KINGSNORTH B 400KV SUBSTATION?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Kingsnorth 400kV: 2,850 MW waiting
- Kingsnorth 132kV: 180 MW waiting
- NorthFleet 400kV: 300 MW waiting
- North Kent Connection Node C 400kV: 532 MW waiting
- Coryton South 400kV: 1,000 MW waiting