Rayleigh 400kV: grid connection queue

Rayleigh 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

2 projects with 1,530 MW are waiting to connect here (largest by capacity: mixed and other, battery storage). Contracted dates run from 30 Jun 2028 to 31 Oct 2032.

2projects in the queue
1,530 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
480 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Gresham House Rayleigh BESSRayleigh Storage LimitedBattery storage48030 Jun 2028High30 Jun 2030Scopingnone
Bradwell Energy ParkLOW CARBON SOLAR PARK 28 LIMITEDMixed and other1,05031 Oct 2032Low31 Oct 2032Scopingnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Maldon Causeway Primary 11kVUK Power Networks4.2 km23 MW11 MW
Maldon Grid 33kVUK Power Networks4.6 km62 MW25 MW
Maldon Wick Primary 11kVUK Power Networks4.9 km13 MW6 MW
Tillingham Primary 11kVUK Power Networks10.0 km19 MW13 MW
South Witham Primary 11kVUK Power Networks10.3 km21 MW9.7 MW
Tiptree Primary 11kVUK Power Networks11.6 km14 MW0.4 MW

Thinking of connecting near Rayleigh 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points