Rayleigh Main 400kV: grid connection queue
Rayleigh Main 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
3 projects with 144 MW are waiting to connect here (largest by capacity: solar + storage, battery storage). Contracted dates run from 31 Oct 2028 to 30 Oct 2034.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Rayleigh 1 Tertiary | RAYLEIGH GREEN LIMITED | Solar + storage | 57 | 31 Oct 2028 | High | 31 Oct 2030 | Consents Approved | none |
| Rayleigh 2 Tertiary | ENSO GREEN HOLDINGS J LIMITED | Solar + storage | 57 | 31 Oct 2028 | High | 31 Oct 2030 | Scoping | none |
| Rayleigh GP3 | ENSO GREEN HOLDINGS J LIMITED | Battery storage | 30 | 30 Oct 2034 | Low | 30 Oct 2034 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Maldon Causeway Primary 11kV | UK Power Networks | 4.2 km | 23 MW | 11 MW |
| Maldon Grid 33kV | UK Power Networks | 4.6 km | 62 MW | 25 MW |
| Maldon Wick Primary 11kV | UK Power Networks | 4.9 km | 13 MW | 6 MW |
| Tillingham Primary 11kV | UK Power Networks | 10.0 km | 19 MW | 13 MW |
| South Witham Primary 11kV | UK Power Networks | 10.3 km | 21 MW | 9.7 MW |
| Tiptree Primary 11kV | UK Power Networks | 11.6 km | 14 MW | 0.4 MW |
Thinking of connecting near Rayleigh Main 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Rayleigh 400kV: 1,530 MW waiting
- Rayleigh Main 132kV: 250 MW waiting
- Rayleigh Main: 120 MW waiting
- South Anglia Connection Node D 400kV: 1,000 MW waiting
- South Anglia Connection Node E 400kV: 1,509 MW waiting