South Anglia Connection Node E 400kV: grid connection queue
South Anglia Connection Node E 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
4 projects with 1,509 MW are waiting to connect here (largest by capacity: solar + storage, battery storage). Contracted dates run from 31 Oct 2034 to 31 Oct 2034.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| PVDP Woodbridge | SolarSeven Ltd | Solar + storage | 610 | 31 Oct 2034 | Low | 31 Oct 2034 | Scoping | none |
| Woodbridge - Noventum | NOVENTUM POWER SOLAR 16 LIMITED | Battery storage | 400 | 31 Oct 2034 | Low | 31 Oct 2034 | Scoping | 1 |
| Lime Tree Energy Park | BNRG LANGMEAD LIMITED | Solar + storage | 250 | 31 Oct 2034 | Low | 31 Oct 2034 | Scoping | none |
| Red House Farm - Friston 400kV 249MW connection | CAMBRIDGE POWER LIMITED | Battery storage | 249 | 31 Oct 2034 | Low | 31 Oct 2034 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Tiptree Primary 11kV | UK Power Networks | 4.9 km | 14 MW | 0.4 MW |
| Abberton Grid 33kV | UK Power Networks | 5.6 km | 78 MW | 43 MW |
| Shrub End Primary 11kV | UK Power Networks | 6.5 km | 9.8 MW | 7.9 MW |
| Peldon Primary 11kV | UK Power Networks | 6.6 km | 8.8 MW | 4.1 MW |
| Marks Tey Primary 11kV | UK Power Networks | 7.0 km | 14 MW | 5.2 MW |
| Berechurch Primary 11kV | UK Power Networks | 7.7 km | 21 MW | 12 MW |
Thinking of connecting near South Anglia Connection Node E 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- South Anglia Connection Node A 400kV: 1,240 MW waiting
- South Anglia Connection Node D 400kV: 1,000 MW waiting
- Rayleigh 400kV: 1,530 MW waiting
- Rayleigh Main 132kV: 250 MW waiting
- Rayleigh Main 400kV: 144 MW waiting