Feckenham 400kV: grid connection queue

Feckenham 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

7 projects with 3,375 MW are waiting to connect here (largest by capacity: solar + storage, battery storage). Contracted dates run from 31 Oct 2028 to 30 Oct 2037.

7projects in the queue
3,375 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
1date moves since 2 Jun 2026
150 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Feckenham Greener Grid ParkStatkraft UK LtdBattery storage15031 Oct 2028High31 Oct 2030Scoping1
FeckenhamIGP SOLAR 14 LIMITEDSolar + storage50021 Jul 2029Medium21 Jul 2029Scopingnone
Feckenham Green Energy CentreFECKENHAM GREEN NG LIMITEDSolar + storage1,02530 Oct 2032Low30 Oct 2032Scopingnone
Feckenham Energy ParkGREEN ENERGY MAB LTDBattery storage50031 Oct 2033Low31 Oct 2033Scoping1
Boom Power Feckenham Generation HubWheaten Hill BESS LimitedSolar + storage40031 Oct 2033Low31 Oct 2033Scoping1
FeckenhamENSO GREEN HOLDINGS X LIMITEDSolar + storage40031 Oct 2036Low31 Oct 2036Awaiting Consents1
Feckenham PV & BESS StationIB VOGT UK LTDSolar + storage40030 Oct 2037Low30 Oct 2037Scoping1

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
13 Oct 2026Feckenham PV & BESS Station31 Oct 203330 Oct 2037+48 months

Thinking of connecting near Feckenham 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.