Taynuilt 132/33kV GSP: grid connection queue
Taynuilt 132/33kV GSP Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 35 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 28 Mar 2031 to 28 Mar 2031.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Beinn Ghlas | HEADWIND DEVELOPMENT SERVICES LIMITED | Onshore wind | 35 | 28 Mar 2031 | High | 11 Feb 2033 | Consents Approved | 2 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 0 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 10 Nov 2026 | Beinn Ghlas | 31 Oct 2034 | 28 Mar 2031 | -43 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Lochdonhead Primary | SSEN Distribution | 2.2 km | 0 MW | 0 MW |
| Kerrera Primary | SSEN Distribution | 11.2 km | 0 MW | 0 MW |
| Fishnish Primary | SSEN Distribution | 11.4 km | 0.2 MW | 0.2 MW |
| Lochaline Primary | SSEN Distribution | 13.9 km | 0.7 MW | 4.2 MW |
| Oban Primary | SSEN Distribution | 14.0 km | 0 MW | 0 MW |
| Kilninver Primary | SSEN Distribution | 14.9 km | 0 MW | 0.9 MW |
Thinking of connecting near Taynuilt 132/33kV GSP?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- NEW TAYNUILT 132 KV SUBSTATION: 290 MW waiting
- Craig Murrail: 56 MW waiting
- Balliemeanoch 275kV: 900 MW waiting
- Cruachan 275kV: 640 MW waiting
- Blarghour: 67 MW waiting