Peterhead 400kV: grid connection queue

Peterhead 400kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026

4 projects with 3,110 MW are waiting to connect here (largest by capacity: offshore wind, battery storage). Contracted dates run from 31 Oct 2033 to 31 Oct 2035.

4projects in the queue
3,110 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Buchan 01 Offshore Wind FarmBUCHAN OFFSHORE WIND LIMITEDOffshore wind96031 Oct 2033Low31 Oct 2033Scopingnone
Peterhead BatteryPETERHEAD FLEXPOWER LTDBattery storage50031 Oct 2033Low31 Oct 2033Scoping1
Stirling BESSANESCO LIMITEDBattery storage30031 Oct 2033Low31 Oct 2033Scoping1
CENOSFLOTATION ENERGY LIMITEDOffshore wind1,35031 Oct 2035Low31 Oct 2035Scopingnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Coupar Angus PrimarySSEN Distribution1.6 km0 MW0 MW
Coupar Angus GSPSSEN Distribution1.6 km
Blairgowrie PrimarySSEN Distribution6.2 km0 MW13 MW
Balbeggie PrimarySSEN Distribution9.4 km0 MW4.5 MW
Alyth PrimarySSEN Distribution10.3 km0 MW2.9 MW
Caputh PrimarySSEN Distribution11.2 km0 MW5.9 MW

Thinking of connecting near Peterhead 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.