Coupar Angus 132/33kV: grid connection queue
Coupar Angus 132/33kV GSP · SSEN Transmission (northern Scotland) · register of 26 November 2026
4 projects with 156 MW are waiting to connect here (largest by capacity: solar + storage, solar). Contracted dates run from 21 Feb 2022 to 30 Apr 2027.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Coupar Angus Battery | COUPAR LIMITED | Battery storage | 40 | 21 Feb 2022 | n/a | Consents Approved | none | |
| Keithick Estate | SIRIUS ECODEV (STIRLING) LTD | Solar + storage | 50 | 31 Dec 2026 | High | 30 Dec 2028 | Under Construction/Commissioning | 2 |
| Keithick 16 Solar & BESS | SIRIUS ECODEV (KEITHICK) LTD | Solar + storage | 16 | 31 Dec 2026 | High | 30 Dec 2028 | Consents Approved | 2 |
| Coupar Solar Farm | COUPAR TWO LIMITED | Solar | 50 | 30 Apr 2027 | High | 14 May 2029 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 2 times: 2 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 22 Sep 2026 | Keithick 16 Solar & BESS | 30 Jun 2026 | 31 Dec 2026 | +6 months |
| 1 Sep 2026 | Keithick Estate | 30 Jun 2026 | 31 Dec 2026 | +6 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Dalrulzion Primary | SSEN Distribution | 5.6 km | 0 MW | 0.5 MW |
| Blairgowrie Primary | SSEN Distribution | 11.3 km | 0 MW | 13 MW |
| Caputh Primary | SSEN Distribution | 12.9 km | 0 MW | 5.9 MW |
| Alyth Primary | SSEN Distribution | 13.2 km | 0 MW | 2.9 MW |
| Pitlochry Primary | SSEN Distribution | 16.6 km | 0 MW | 0.7 MW |
| Coupar Angus GSP | SSEN Distribution | 17.4 km |
Thinking of connecting near Coupar Angus 132/33kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Coupar Angus 2: 50 MW waiting
- Alyth 400kV: 1,124 MW waiting
- Alyth Solar and Battery 400/132kV: 900 MW waiting
- ALYTH BESS STATION 400KV SUBSTATION: 500 MW waiting
- Peterhead 400kV: 3,110 MW waiting