Coupar Angus 132/33kV: grid connection queue

Coupar Angus 132/33kV GSP · SSEN Transmission (northern Scotland) · register of 26 November 2026

4 projects with 156 MW are waiting to connect here (largest by capacity: solar + storage, solar). Contracted dates run from 21 Feb 2022 to 30 Apr 2027.

4projects in the queue
156 MWwaiting to connect
18 MWalready connected
66 MWholding Gate 2
2date moves since 2 Jun 2026
116 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Coupar Angus BatteryCOUPAR LIMITEDBattery storage4021 Feb 2022n/aConsents Approvednone
Keithick EstateSIRIUS ECODEV (STIRLING) LTDSolar + storage5031 Dec 2026High30 Dec 2028Under Construction/Commissioning2
Keithick 16 Solar & BESSSIRIUS ECODEV (KEITHICK) LTDSolar + storage1631 Dec 2026High30 Dec 2028Consents Approved2
Coupar Solar FarmCOUPAR TWO LIMITEDSolar5030 Apr 2027High14 May 2029Scoping1

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 2 times: 2 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
22 Sep 2026Keithick 16 Solar & BESS30 Jun 202631 Dec 2026+6 months
1 Sep 2026Keithick Estate30 Jun 202631 Dec 2026+6 months

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Dalrulzion PrimarySSEN Distribution5.6 km0 MW0.5 MW
Blairgowrie PrimarySSEN Distribution11.3 km0 MW13 MW
Caputh PrimarySSEN Distribution12.9 km0 MW5.9 MW
Alyth PrimarySSEN Distribution13.2 km0 MW2.9 MW
Pitlochry PrimarySSEN Distribution16.6 km0 MW0.7 MW
Coupar Angus GSPSSEN Distribution17.4 km

Thinking of connecting near Coupar Angus 132/33kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points