ALYTH BESS STATION 400KV SUBSTATION: grid connection queue
ALYTH BESS STATION 400KV SUBSTATION · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 500 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2033 to 31 Oct 2033.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Alyth BESS Station | IGP INTERNATIONAL PROSPECTING LIMITED | Battery storage | 500 | 31 Oct 2033 | Low | 31 Oct 2033 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Alyth Primary | SSEN Distribution | 1.1 km | 0 MW | 2.9 MW |
| Blairgowrie Primary | SSEN Distribution | 7.1 km | 0 MW | 13 MW |
| Coupar Angus GSP | SSEN Distribution | 9.7 km | ||
| Coupar Angus Primary | SSEN Distribution | 9.7 km | 0 MW | 0 MW |
| Dalrulzion Primary | SSEN Distribution | 14.7 km | 0 MW | 0.5 MW |
| Maryton Primary | SSEN Distribution | 15.3 km | 0 MW | 7.4 MW |
Thinking of connecting near ALYTH BESS STATION 400KV SUBSTATION?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Alyth 400kV: 1,124 MW waiting
- Alyth Solar and Battery 400/132kV: 900 MW waiting
- Peterhead 400kV: 3,110 MW waiting
- Coupar Angus 132/33kV: 156 MW waiting
- Coupar Angus 2: 50 MW waiting