Coalburn 132kV: grid connection queue

Coalburn 132kV · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 112 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 28 Apr 2028 to 28 Apr 2028.

1project in the queue
112 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
112 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Kennoxhead Wind FarmPERIGUS ENERGY UK LIMITEDOnshore wind11228 Apr 2028High26 Jun 2030Consents Approvednone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Douglas WestSP Energy Networks3.9 km22 MW15 MW
LesmahagowSP Energy Networks5.6 km10 MW15 MW
Corra LinnSP Energy Networks10.2 km4.6 MW8 MW
LanarkSP Energy Networks12.0 km26 MW17 MW
StonehouseSP Energy Networks12.9 km19 MW1 MW
BraidwoodSP Energy Networks13.8 km12 MW

Thinking of connecting near Coalburn 132kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points