Coalburn North 400kV: grid connection queue
Coalburn North 400kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 200 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Aug 2027 to 31 Aug 2027.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Zenobe Coalburn Battery Storage | Zenobe Coalburn Limited | Battery storage | 200 | 31 Aug 2027 | High | 30 Aug 2029 | Consents Approved | 2 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Douglas West | SP Energy Networks | 3.9 km | 22 MW | 15 MW |
| Lesmahagow | SP Energy Networks | 5.6 km | 10 MW | 15 MW |
| Corra Linn | SP Energy Networks | 10.2 km | 4.6 MW | 8 MW |
| Lanark | SP Energy Networks | 12.0 km | 26 MW | 17 MW |
| Stonehouse | SP Energy Networks | 12.9 km | 19 MW | 1 MW |
| Braidwood | SP Energy Networks | 13.8 km | 12 MW |
Thinking of connecting near Coalburn North 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Coalburn 400kV GIS: 500 MW waiting
- Coalburn 132kV: 112 MW waiting
- M74 West Wind Farm 132kV: 180 MW waiting
- Bodinglee Wind Farm 132kV: 280 MW waiting
- Hare Craig 33kV: 46 MW waiting