Coalburn 400kV GIS: grid connection queue

Coalburn 400kV GIS Substation · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 500 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Aug 2027 to 31 Aug 2027.

1project in the queue
500 MWwaiting to connect
0 MWalready connected
500 MWholding Gate 2
1date moves since 2 Jun 2026
500 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Rawhills Battery Energy Storage Facility(Coalburn 2)ALCEMI STORAGE DEVELOPMENTS 6 LIMITEDBattery storage50031 Aug 2027High30 Aug 2029Consents Approved2

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
23 Jun 2026Rawhills Battery Energy Storage Facility16 Apr 202731 Aug 2027+4 months

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Douglas WestSP Energy Networks3.9 km22 MW15 MW
LesmahagowSP Energy Networks5.6 km10 MW15 MW
Corra LinnSP Energy Networks10.2 km4.6 MW8 MW
LanarkSP Energy Networks12.0 km26 MW17 MW
StonehouseSP Energy Networks12.9 km19 MW1 MW
BraidwoodSP Energy Networks13.8 km12 MW

Thinking of connecting near Coalburn 400kV GIS?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points