Hare Craig 33kV: grid connection queue

Hare Craig 33kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 46 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 31 Oct 2028 to 31 Oct 2028.

1project in the queue
46 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
46 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Hare Craig Wind FarmHARE CRAIG WINDFARM LLPOnshore wind4631 Oct 2028High29 Dec 2030Awaiting Consentsnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Douglas WestSP Energy Networks7.9 km22 MW15 MW
CronberrySP Energy Networks9.8 km7.9 MW7.3 MW
LesmahagowSP Energy Networks12.1 km10 MW15 MW
StrathavenSP Energy Networks14.2 km24 MW13 MW
StonehouseSP Energy Networks15.6 km19 MW1 MW
Corra LinnSP Energy Networks18.0 km4.6 MW8 MW

Thinking of connecting near Hare Craig 33kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points