Glen Ullinish 132/33kV: grid connection queue

Glen Ullinish 132/33kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026

1 project with 50 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 25 Nov 2031 to 25 Nov 2031.

1project in the queue
50 MWwaiting to connect
0 MWalready connected
50 MWholding Gate 2
1date moves since 2 Jun 2026
50 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Glen Ullinish Wind FarmGLEN ULLINISH WF LIMITEDOnshore wind5025 Nov 2031High11 Oct 2033Consents Approved2

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
8 Sep 2026Glen Ullinish Wind Farm31 Oct 202616 Apr 2028+18 months

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Dunvegan PrimarySSEN Distribution8.6 km0 MW0 MW
Dunvegan GSPSSEN Distribution8.6 km
Drynoch PrimarySSEN Distribution12.8 km0.7 MW0 MW
Portree PrimarySSEN Distribution13.4 km0 MW0 MW
Lower Ollach PrimarySSEN Distribution17.3 km1 MW0 MW

Thinking of connecting near Glen Ullinish 132/33kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.