Edinbane 132/33kV: grid connection queue

Edinbane 132/33kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026

2 projects with 88 MW are waiting to connect here (largest by capacity: onshore wind + storage, onshore wind). Contracted dates run from 30 Apr 2033 to 31 Oct 2034.

2projects in the queue
88 MWwaiting to connect
41 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Edinbane WindfarmVATTENFALL WIND POWER LTDOnshore wind + storage4930 Apr 2033Low30 Apr 2033Scoping1
GlenmoreAEUK WIND PROJECT II LTDOnshore wind4031 Oct 2034Low31 Oct 2034Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Dunvegan GSPSSEN Distribution7.9 km
Dunvegan PrimarySSEN Distribution7.9 km0 MW0 MW
Uig PrimarySSEN Distribution14.2 km0 MW0 MW
Portree PrimarySSEN Distribution15.0 km0 MW0 MW
Ardmore GSPSSEN Distribution15.9 km

Thinking of connecting near Edinbane 132/33kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points