Glen Ullinish Extension 132/33kV: grid connection queue
Glen Ullinish Extension 132/33kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 240 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 25 Nov 2031 to 25 Nov 2031.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Glen Ullinish Extension | GLEN ULLINISH WF 2 LTD | Onshore wind | 240 | 25 Nov 2031 | High | 11 Oct 2033 | Awaiting Consents | 2 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 2 times: 2 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 3 Nov 2026 | Glen Ullinish Extension | 31 Aug 2029 | 25 Nov 2031 | +27 months |
| 8 Sep 2026 | Glen Ullinish Extension | 1 Apr 2027 | 31 Aug 2029 | +29 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Dunvegan Primary | SSEN Distribution | 8.6 km | 0 MW | 0 MW |
| Dunvegan GSP | SSEN Distribution | 8.6 km | ||
| Drynoch Primary | SSEN Distribution | 12.8 km | 0.7 MW | 0 MW |
| Portree Primary | SSEN Distribution | 13.4 km | 0 MW | 0 MW |
| Lower Ollach Primary | SSEN Distribution | 17.3 km | 1 MW | 0 MW |
Thinking of connecting near Glen Ullinish Extension 132/33kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Glen Ullinish 132/33kV: 50 MW waiting
- Dunvegan 132/33kV Grid Supply Point: 25 MW waiting
- Edinbane 132/33kV: 88 MW waiting
- Abhainn Dubh Wind Farm 132kV: 75 MW waiting
- Broadford 132kV: 200 MW waiting