Broadford 132kV: grid connection queue
Broadford 132kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 200 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2034 to 31 Oct 2034.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Broadford BESS | FIELD DEVCO LTD | Battery storage | 200 | 31 Oct 2034 | Low | 31 Oct 2034 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Kyle Primary | SSEN Distribution | 1.4 km | 4.8 MW | 0 MW |
| Nostie Bridge Primary | SSEN Distribution | 7.4 km | 1.2 MW | 0 MW |
| Skulamus Primary | SSEN Distribution | 13.0 km | 1.4 MW | 0 MW |
| Broadford GSP | SSEN Distribution | 15.5 km | ||
| Broadford Primary | SSEN Distribution | 15.5 km | 4.8 MW | 0 MW |
| Kishornhill Primary | SSEN Distribution | 16.7 km | 0.7 MW | 0 MW |
Thinking of connecting near Broadford 132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Broadford: 100 MW waiting
- Breakish 132kV: 100 MW waiting
- Abhainn Dubh Wind Farm 132kV: 75 MW waiting
- Dunvegan 132/33kV Grid Supply Point: 25 MW waiting
- Glen Ullinish Extension 132/33kV: 240 MW waiting