St Fergus Mobil 132/11kV: grid connection queue
St Fergus Mobil 132/11kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 20 MW is waiting to connect here (largest by capacity: solar). Contracted dates run from 30 Apr 2029 to 30 Apr 2029.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| SAGE | SAGE NORTH SEA LIMITED | Solar | 20 | 30 Apr 2029 | Medium | 30 Apr 2029 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 13 Oct 2026 | SAGE | 30 Jun 2025 | 30 Apr 2029 | +46 months |
Thinking of connecting near St Fergus Mobil 132/11kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.