Bradford West 275kV: grid connection queue

Bradford West 275kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

3 projects with 849 MW are waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 May 2027 to 24 Oct 2036.

3projects in the queue
849 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
100 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Bradford West 100MWOLD ALLEN ROAD BESS LIMITEDBattery storage10031 May 2027High30 May 2029Consents Approvednone
Holdsworth RoadMAS 002 LIMITEDBattery storage50024 Oct 2036Low24 Oct 2036Consents Approvednone
Bradford West BESS SubstationO&G Solar (SPV 36) LimitedBattery storage24924 Oct 2036Low24 Oct 2036Scopingnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Primary substation 400056Electricity North West16.2 km0 MW9.9 MW

Thinking of connecting near Bradford West 275kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points