Lorg Wind Farm 132/32kV: grid connection queue
Lorg Wind Farm 132/32kV · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 70 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 7 Apr 2028 to 7 Apr 2028.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Lorg Wind Farm | RWE Renewables UK Onshore Wind Limited | Onshore wind | 70 | 7 Apr 2028 | High | 5 Jun 2030 | Awaiting Consents | none |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 8 Sep 2026 | Lorg Wind Farm | 7 Apr 2027 | 7 Apr 2028 | +12 months |
Thinking of connecting near Lorg Wind Farm 132/32kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.