Strathleven: grid connection queue
Strathleven GSP · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 200 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 22 May 2031 to 22 May 2031.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Murroch BESS | Apatura Battery Ltd | Battery storage | 200 | 22 May 2031 | Medium | 22 May 2031 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Drymen Primary | SSEN Distribution | 5.4 km | 0 MW | 4.2 MW |
| Kepculloch Primary | SSEN Distribution | 6.9 km | 0 MW | 2.3 MW |
| Killearn Primary | SSEN Distribution | 7.7 km | 0 MW | 3.7 MW |
| Aberfoyle Primary | SSEN Distribution | 8.8 km | 0 MW | 3.5 MW |
| Blairlinnans Primary | SSEN Distribution | 10.4 km | 0 MW | 2.4 MW |
| Balloch | SP Energy Networks | 14.4 km | 27 MW | 11 MW |
Thinking of connecting near Strathleven?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Drumchapel 275/33kV: 60 MW waiting
- Vale of Leven 132kV substation: 72 MW waiting
- Windyhill 132kV: 200 MW waiting
- Helensburgh 132/33kV: 40 MW waiting
- Killermont: 43 MW waiting