Helensburgh 132/33kV: grid connection queue

Helensburgh 132/33kV · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 40 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 29 Oct 2027 to 29 Oct 2027.

1project in the queue
40 MWwaiting to connect
0 MWalready connected
40 MWholding Gate 2
0date moves since 2 Jun 2026
40 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Drumfad Battery Storage SystemEKU ENERGY FAUNE PROJECTS (UK) LIMITEDBattery storage4029 Oct 2027High28 Oct 2029Consents Approved2

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
WoodendSP Energy Networks2.2 km12 MW3.9 MW
CraigendoranSP Energy Networks4.7 km27 MW13 MW
Dumfin 11kV NetworkSSEN Distribution5.8 km0.5 MW4.2 MW
GarelochheadSP Energy Networks7.1 km10 MW8.1 MW
CaddlehillSP Energy Networks9.3 km12 MW
Baker StreetSP Energy Networks9.9 km27 MW13 MW

Thinking of connecting near Helensburgh 132/33kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points