Devol Moor 400/132kV: grid connection queue

Devol Moor 400/132kV · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 400 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 27 Sep 2027 to 27 Sep 2027.

1project in the queue
400 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
1date moves since 2 Jun 2026
400 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Devol Moor Battery & Solar ProjectSunshine Project 03 LimitedBattery storage40027 Sep 2027High26 Sep 2029Scoping1

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 0 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
29 Sep 2026Devol Moor Battery & Solar Project17 Oct 202927 Sep 2027-25 months

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Boundary StreetSP Energy Networks0.5 km26 MW14 MW
Baker StreetSP Energy Networks2.3 km27 MW13 MW
Port GlasgowSP Energy Networks3.2 km20 MW6.6 MW
CaddlehillSP Energy Networks3.8 km12 MW
Inverkip RoadSP Energy Networks7.2 km22 MW17 MW
CraigendoranSP Energy Networks7.3 km27 MW13 MW

Thinking of connecting near Devol Moor 400/132kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.