BEAULY 02 BESS 132kV SUBSTATION: grid connection queue
BEAULY 02 BESS 132kV SUBSTATION · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 100 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Dec 2028 to 31 Dec 2028.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Beauly 02 BESS | FIELD BEAULY LTD | Battery storage | 100 | 31 Dec 2028 | Medium | 31 Dec 2028 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 2 times: 1 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 20 Oct 2026 | Beauly 02 BESS | 31 Oct 2028 | 31 Dec 2028 | +2 months |
| 13 Oct 2026 | Beauly 02 BESS | 31 Dec 2028 | 31 Oct 2028 | -2 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Orrin GSP | SSEN Distribution | 4.4 km | ||
| Marybank Primary | SSEN Distribution | 5.1 km | 0 MW | 0 MW |
| Comrie Primary | SSEN Distribution | 6.2 km | 0 MW | 0 MW |
| Beauly GSP | SSEN Distribution | 9.1 km | ||
| Aigas Primary | SSEN Distribution | 9.9 km | 0 MW | 0 MW |
| Muir of Ord Primary | SSEN Distribution | 10.2 km | 0 MW | 0 MW |
Thinking of connecting near BEAULY 02 BESS 132kV SUBSTATION?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Orrin: 101 MW waiting
- Beauly substation 275KV: 77 MW waiting
- Beauly 132/33 kV GSP: 50 MW waiting
- Fairburn Extension 132/33kV: 90 MW waiting
- Carn Fearna Wind Farm 132/33kV: 85 MW waiting