BEAULY 02 BESS 132kV SUBSTATION: grid connection queue

BEAULY 02 BESS 132kV SUBSTATION · SSEN Transmission (northern Scotland) · register of 26 November 2026

1 project with 100 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Dec 2028 to 31 Dec 2028.

1project in the queue
100 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
2date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Beauly 02 BESSFIELD BEAULY LTDBattery storage10031 Dec 2028Medium31 Dec 2028Scoping1

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 2 times: 1 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
20 Oct 2026Beauly 02 BESS31 Oct 202831 Dec 2028+2 months
13 Oct 2026Beauly 02 BESS31 Dec 202831 Oct 2028-2 months

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Orrin GSPSSEN Distribution4.4 km
Marybank PrimarySSEN Distribution5.1 km0 MW0 MW
Comrie PrimarySSEN Distribution6.2 km0 MW0 MW
Beauly GSPSSEN Distribution9.1 km
Aigas PrimarySSEN Distribution9.9 km0 MW0 MW
Muir of Ord PrimarySSEN Distribution10.2 km0 MW0 MW

Thinking of connecting near BEAULY 02 BESS 132kV SUBSTATION?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points