Orrin: grid connection queue
Orrin GSP · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 101 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 31 Oct 2033 to 31 Oct 2033.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Statkraft SEWF | Statkraft UK Ltd | Onshore wind | 101 | 31 Oct 2033 | Low | 31 Oct 2033 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Orrin GSP | SSEN Distribution | 4.4 km | ||
| Marybank Primary | SSEN Distribution | 5.1 km | 0 MW | 0 MW |
| Comrie Primary | SSEN Distribution | 6.2 km | 0 MW | 0 MW |
| Beauly GSP | SSEN Distribution | 9.1 km | ||
| Aigas Primary | SSEN Distribution | 9.9 km | 0 MW | 0 MW |
| Muir of Ord Primary | SSEN Distribution | 10.2 km | 0 MW | 0 MW |
Thinking of connecting near Orrin?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- BEAULY 02 BESS 132kV SUBSTATION: 100 MW waiting
- Beauly substation 275KV: 77 MW waiting
- Beauly 132/33 kV GSP: 50 MW waiting
- Fairburn Extension 132/33kV: 90 MW waiting
- Carn Fearna Wind Farm 132/33kV: 85 MW waiting