Loch Liath 132/33kV: grid connection queue

Loch Liath 132/33kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026

1 project with 99 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 31 Oct 2035 to 31 Oct 2035.

1project in the queue
99 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Loch Liath Wind FarmLOCH LIATH WIND FARM LIMITEDOnshore wind9931 Oct 2035Low31 Oct 2035Awaiting Consents1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Drumnadrochit PrimarySSEN Distribution0.7 km0 MW2 MW
Foyers PrimarySSEN Distribution8.1 km0 MW0 MW
Errogie PrimarySSEN Distribution8.8 km0 MW0 MW
Kiltarlity PrimarySSEN Distribution12.1 km0 MW0 MW
Aigas PrimarySSEN Distribution12.5 km0 MW0 MW
Beauly GSPSSEN Distribution15.6 km

Thinking of connecting near Loch Liath 132/33kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points