Glen Earrach PSH 400kV substation: grid connection queue
Glen Earrach PSH 400kV substation · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 1,800 MW is waiting to connect here (largest by capacity: hydro, pumped storage and tidal). Contracted dates run from 31 Oct 2035 to 31 Oct 2035.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Glen Earrach PSH | GLEN EARRACH ENERGY LIMITED | Hydro, pumped storage and tidal | 1,800 | 31 Oct 2035 | Low | 31 Oct 2035 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Drumnadrochit Primary | SSEN Distribution | 5.6 km | 0 MW | 2 MW |
| Foyers Primary | SSEN Distribution | 8.4 km | 0 MW | 0 MW |
| Aigas Primary | SSEN Distribution | 12.5 km | 0 MW | 0 MW |
| Errogie Primary | SSEN Distribution | 12.8 km | 0 MW | 0 MW |
| Fasnakyle GSP | SSEN Distribution | 13.2 km | ||
| Fasnakyle Primary | SSEN Distribution | 13.2 km | 0.9 MW | 0.6 MW |
Thinking of connecting near Glen Earrach PSH 400kV substation?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Loch Liath 132/33kV: 99 MW waiting
- Bhlaraidh 132/33kV: 101 MW waiting
- Loch Kemp 275kV Switching Station: 660 MW waiting
- Cloiche 132/33kV: 200 MW waiting
- Loch na Cathrach 275kV Switching Station: 550 MW waiting