Lairdmannoch Energy Park 132kV substation: grid connection queue
Lairdmannoch Energy Park 132kV substation · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 100 MW is waiting to connect here (largest by capacity: mixed and other). Contracted dates run from 28 Jun 2030 to 28 Jun 2030.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Lairdmannoch Energy Park | LAIRDMANNOCH ENERGY PARK LIMITED | Mixed and other | 100 | 28 Jun 2030 | Medium | 28 Jun 2030 | Awaiting Consents | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Gatehouse | SP Energy Networks | 8.1 km | 7.9 MW | 5.4 MW |
| Tongland Distribution | SP Energy Networks | 9.0 km | 17 MW | 8.2 MW |
| Castle Douglas | SP Energy Networks | 11.7 km | 7.3 MW | 3.8 MW |
| Dalbeattie | SP Energy Networks | 17.5 km | 12 MW | 11 MW |
| Creetown | SP Energy Networks | 18.0 km | 7.8 MW | 8.7 MW |
| Glenlee Hydro | SP Energy Networks | 19.5 km | 30 MW | 28 MW |
Thinking of connecting near Lairdmannoch Energy Park 132kV substation?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Tongland 132/11kV: 36 MW waiting
- Divot Hill 132/33 kV: 63 MW waiting
- Newton Stewart: 73 MW waiting
- SPT Margree collector substation: 145 MW waiting
- Margree 132/33kV Collector: 68 MW waiting