Tongland 132/11kV: grid connection queue
Tongland 132/11kV · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 36 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 14 Jun 2030 to 14 Jun 2030.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| St Marys Isle Solar Farm | GRUPOTEC SOLAR UK 5 LIMITED | Solar + storage | 36 | 14 Jun 2030 | Medium | 14 Jun 2030 | Consents Approved | 2 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Tongland Distribution | SP Energy Networks | 2.4 km | 17 MW | 8.2 MW |
| Gatehouse | SP Energy Networks | 9.7 km | 7.9 MW | 5.4 MW |
| Castle Douglas | SP Energy Networks | 14.1 km | 7.3 MW | 3.8 MW |
| Dalbeattie | SP Energy Networks | 18.0 km | 12 MW | 11 MW |
Thinking of connecting near Tongland 132/11kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Lairdmannoch Energy Park 132kV substation: 100 MW waiting
- Newton Stewart: 73 MW waiting
- BLAIR HILL WIND FARM 132KV SUBSTATION: 99 MW waiting
- Divot Hill 132/33 kV: 63 MW waiting
- SPT Margree collector substation: 145 MW waiting