132kV bay at Iron Acton: grid connection queue

132kV bay at Iron Acton Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

1 project with 21 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 30 Sep 2026 to 30 Sep 2026.

1project in the queue
21 MWwaiting to connect
99 MWalready connected
21 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Iron ActonIRON ACTON GREEN LIMITEDSolar + storage2130 Sep 2026n/aConsents Approved2

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Alderton PrimarySSEN Distribution17.7 km0 MW0 MW

Thinking of connecting near 132kV bay at Iron Acton?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.