Severn Connection Node A 400kv: grid connection queue

Severn Connection Node A 400kv Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

5 projects with 1,338 MW are waiting to connect here (largest by capacity: mixed and other, battery storage). Contracted dates run from 31 Oct 2037 to 31 Oct 2038.

5projects in the queue
1,338 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Stockhills FarmBSR APPLICATIONS LIMITEDMixed and other80031 Oct 2037Low31 Oct 2037Scoping1
Lightsource Folly FarmLightsource Renewable UK Development LimitedOnshore wind + storage24031 Oct 2037Low31 Oct 2037Scoping1
KX Alpha 3 Iron ActonKXP ALPHA III LIMITEDBattery storage10031 Oct 2037Low31 Oct 2037Scoping1
KX Alpha 1 Iron ActonKXP ALPHA I LIMITEDBattery storage9931 Oct 2037Low31 Oct 2037Scoping1
KX Alpha 2 Iron ActonKXP ALPHA II LIMITEDBattery storage9931 Oct 2038Low31 Oct 2038Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Alderton PrimarySSEN Distribution16.3 km0 MW0 MW

Thinking of connecting near Severn Connection Node A 400kv?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.