Severn Connection Node A 400kv: grid connection queue
Severn Connection Node A 400kv Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
5 projects with 1,338 MW are waiting to connect here (largest by capacity: mixed and other, battery storage). Contracted dates run from 31 Oct 2037 to 31 Oct 2038.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Stockhills Farm | BSR APPLICATIONS LIMITED | Mixed and other | 800 | 31 Oct 2037 | Low | 31 Oct 2037 | Scoping | 1 |
| Lightsource Folly Farm | Lightsource Renewable UK Development Limited | Onshore wind + storage | 240 | 31 Oct 2037 | Low | 31 Oct 2037 | Scoping | 1 |
| KX Alpha 3 Iron Acton | KXP ALPHA III LIMITED | Battery storage | 100 | 31 Oct 2037 | Low | 31 Oct 2037 | Scoping | 1 |
| KX Alpha 1 Iron Acton | KXP ALPHA I LIMITED | Battery storage | 99 | 31 Oct 2037 | Low | 31 Oct 2037 | Scoping | 1 |
| KX Alpha 2 Iron Acton | KXP ALPHA II LIMITED | Battery storage | 99 | 31 Oct 2038 | Low | 31 Oct 2038 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Alderton Primary | SSEN Distribution | 16.3 km | 0 MW | 0 MW |
Thinking of connecting near Severn Connection Node A 400kv?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- 132kV bay at Iron Acton: 21 MW waiting
- Severn Connection Node A 132kV: 210 MW waiting
- Iron Acton 275kV: 120 MW waiting
- Iron Acton 132kV: 100 MW waiting
- Severn Connection Node B 400kV: 249 MW waiting