Benzene

Garlogie Production C 275/33kV: grid connection queue

Garlogie Production C 275/33kV GSP · SSEN Transmission (northern Scotland) · register of 26 November 2026

2 projects with 100 MW are waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 31 Oct 2033 to 31 Oct 2033.

2projects in the queue
100 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Garlogie C-1GARLOGIE ENERGY CENTRE LIMITEDSolar + storage5031 Oct 2033Low31 Oct 2033Scoping1
Garlogie C-2GARLOGIE ENERGY CENTRE LIMITEDSolar + storage5031 Oct 2033Low31 Oct 2033Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Thinking of connecting near Garlogie Production C 275/33kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.