New North West 132kV: grid connection queue
New North West 132kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026
2 projects with 299 MW are waiting to connect here (largest by capacity: onshore wind + storage). Contracted dates run from 31 Oct 2037 to 31 Oct 2037.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Meall Dearg | ENERGYFARM UK MEALL DEARG LTD | Onshore wind + storage | 150 | 31 Oct 2037 | Low | 31 Oct 2037 | Scoping | none |
| Ballach | ENERGYFARM UK BALLACH LTD | Onshore wind + storage | 149 | 31 Oct 2037 | Low | 31 Oct 2037 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Aberfeldy Primary | SSEN Distribution | 10.7 km | 0 MW | 3.7 MW |
| Coshieville Primary | SSEN Distribution | 15.2 km | 0 MW | 0 MW |
| Crieff Primary | SSEN Distribution | 17.1 km | 0 MW | 5 MW |
Thinking of connecting near New North West 132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Glen Lednock 132kV: 165 MW waiting
- GLENTARKEN WIND FARM 132/33KV SUBSTATION: 104 MW waiting
- Coupar Angus 132/33kV: 156 MW waiting
- Coupar Angus 2: 50 MW waiting
- Braco West: 75 MW waiting