GLENTARKEN WIND FARM 132/33KV SUBSTATION: grid connection queue

GLENTARKEN WIND FARM 132/33KV SUBSTATION · SSEN Transmission (northern Scotland) · register of 26 November 2026

1 project with 104 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 30 Nov 2031 to 30 Nov 2031.

1project in the queue
104 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Glentarken Wind FarmSSE Renewables Services (UK) LimitedOnshore wind10430 Nov 2031Low30 Nov 2031Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
St Fillans GSPSSEN Distribution6.0 km
Lochearnhead PrimarySSEN Distribution8.5 km0 MW0 MW
Killin Town PrimarySSEN Distribution9.1 km0 MW0 MW
Killin GSPSSEN Distribution10.0 km
Dalchonzie PrimarySSEN Distribution11.4 km0 MW4.4 MW
Ardchyle PrimarySSEN Distribution12.7 km0 MW0 MW

Thinking of connecting near GLENTARKEN WIND FARM 132/33KV SUBSTATION?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points