Killin 132/11kV: grid connection queue
Killin 132/11kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 18 MW is waiting to connect here (largest by capacity: hydro, pumped storage and tidal). Contracted dates run from 30 Nov 2031 to 30 Nov 2031.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Finlarig | SSE GENERATION LIMITED | Hydro, pumped storage and tidal | 18 | 30 Nov 2031 | Low | 30 Nov 2031 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Killin Town Primary | SSEN Distribution | 2.5 km | 0 MW | 0 MW |
| Killin GSP | SSEN Distribution | 2.9 km | ||
| Ardchyle Primary | SSEN Distribution | 3.4 km | 0 MW | 0 MW |
| Lochearnhead Primary | SSEN Distribution | 9.1 km | 0 MW | 0 MW |
| Chaorach Primary | SSEN Distribution | 10.2 km | 0 MW | 0 MW |
| Cashlie Primary | SSEN Distribution | 10.6 km | 0 MW | 1 MW |
Thinking of connecting near Killin 132/11kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Killin: 43 MW waiting
- Lochay 132/11kV: 6 MW waiting
- GLENTARKEN WIND FARM 132/33KV SUBSTATION: 104 MW waiting
- Glen Lednock 132kV: 165 MW waiting
- Rannoch: 20 MW waiting