Killin: grid connection queue
Killin GSP · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 43 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2031 to 31 Oct 2031.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Boreland BESS | BORELAND ENERGY LTD | Battery storage | 43 | 31 Oct 2031 | Medium | 31 Oct 2031 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Killin Town Primary | SSEN Distribution | 2.5 km | 0 MW | 0 MW |
| Killin GSP | SSEN Distribution | 2.9 km | ||
| Ardchyle Primary | SSEN Distribution | 3.4 km | 0 MW | 0 MW |
| Lochearnhead Primary | SSEN Distribution | 9.1 km | 0 MW | 0 MW |
| Chaorach Primary | SSEN Distribution | 10.2 km | 0 MW | 0 MW |
| Cashlie Primary | SSEN Distribution | 10.6 km | 0 MW | 1 MW |
Thinking of connecting near Killin?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Killin 132/11kV: 18 MW waiting
- Lochay 132/11kV: 6 MW waiting
- GLENTARKEN WIND FARM 132/33KV SUBSTATION: 104 MW waiting
- Glen Lednock 132kV: 165 MW waiting
- Rannoch: 20 MW waiting