Glen Lednock 132kV: grid connection queue
Glen Lednock 132kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 165 MW is waiting to connect here (largest by capacity: onshore wind + storage). Contracted dates run from 30 Nov 2031 to 30 Nov 2031.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Glen Lednock | Glen Lednock Wind Farm Limited | Onshore wind + storage | 165 | 30 Nov 2031 | Low | 30 Nov 2031 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 13 Oct 2026 | Glen Lednock | 31 Oct 2031 | 30 Nov 2031 | +1 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| St Fillans GSP | SSEN Distribution | 6.2 km | ||
| Killin Town Primary | SSEN Distribution | 10.5 km | 0 MW | 0 MW |
| Lochearnhead Primary | SSEN Distribution | 10.5 km | 0 MW | 0 MW |
| Dalchonzie Primary | SSEN Distribution | 11.0 km | 0 MW | 4.4 MW |
| Killin GSP | SSEN Distribution | 11.2 km | ||
| Ardchyle Primary | SSEN Distribution | 14.5 km | 0 MW | 0 MW |
Thinking of connecting near Glen Lednock 132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- GLENTARKEN WIND FARM 132/33KV SUBSTATION: 104 MW waiting
- Killin: 43 MW waiting
- Killin 132/11kV: 18 MW waiting
- Lochay 132/11kV: 6 MW waiting
- New North West 132kV: 299 MW waiting