Braco West: grid connection queue

Braco West GSP · SSEN Transmission (northern Scotland) · register of 26 November 2026

1 project with 75 MW is waiting to connect here (largest by capacity: onshore wind + storage). Contracted dates run from 31 Oct 2035 to 31 Oct 2035.

1project in the queue
75 MWwaiting to connect
74 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
WindburnWINDBURN WIND FARM LIMITEDOnshore wind + storage7531 Oct 2035Low31 Oct 2035Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Braco West GSPSSEN Distribution4.2 km
Gleneagles PrimarySSEN Distribution8.1 km0 MW1.8 MW
Dunblane PrimarySSEN Distribution9.9 km0 MW0 MW
Crieff PrimarySSEN Distribution12.7 km0 MW5 MW
MenstrieSP Energy Networks13.4 km27 MW7.6 MW
Stirling UniversitySP Energy Networks13.8 km11 MW

Thinking of connecting near Braco West?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points