Windyhill 275/132kV: grid connection queue
Windyhill 275/132kV · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 200 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 27 Jul 2025 to 27 Jul 2025.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| WindyHill BESS2 Facility | Windyhill Grid 2 Ltd | Battery storage | 200 | 27 Jul 2025 | n/a | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Dunscore | SP Energy Networks | 11.6 km | 7.9 MW | 8.5 MW |
| Penpont | SP Energy Networks | 11.7 km | 3.5 MW | |
| Kirkbank | SP Energy Networks | 13.1 km | 10 MW | 5.3 MW |
| Heathhall | SP Energy Networks | 13.8 km | 18 MW | 11 MW |
| Heathfield | SP Energy Networks | 13.8 km | 13 MW | |
| Lochside | SP Energy Networks | 14.4 km | 11 MW | 7.1 MW |
Thinking of connecting near Windyhill 275/132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Harestanes West Wind Farm 132/33kV: 119 MW waiting
- Watchman 132kV: 250 MW waiting
- Daer Wind Farm 132/33kV: 96 MW waiting
- Dumfries North 400kV: 200 MW waiting
- Dumfries 132/33kV: 90 MW waiting