Windyhill 275/132kV: grid connection queue

Windyhill 275/132kV · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 200 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 27 Jul 2025 to 27 Jul 2025.

1project in the queue
200 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
WindyHill BESS2 FacilityWindyhill Grid 2 LtdBattery storage20027 Jul 2025n/aScoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
DunscoreSP Energy Networks11.6 km7.9 MW8.5 MW
PenpontSP Energy Networks11.7 km3.5 MW
KirkbankSP Energy Networks13.1 km10 MW5.3 MW
HeathhallSP Energy Networks13.8 km18 MW11 MW
HeathfieldSP Energy Networks13.8 km13 MW
LochsideSP Energy Networks14.4 km11 MW7.1 MW

Thinking of connecting near Windyhill 275/132kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.