Watchman 132kV: grid connection queue
Watchman 132kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 250 MW is waiting to connect here (largest by capacity: mixed and other). Contracted dates run from 31 Oct 2036 to 31 Oct 2036.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Watchman Energy Park | RENEWCO POWER LIMITED | Mixed and other | 250 | 31 Oct 2036 | Low | 31 Oct 2036 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Moffat | SP Energy Networks | 14.6 km | 8.5 MW | 3.6 MW |
| Penpont | SP Energy Networks | 14.9 km | 3.5 MW |
Thinking of connecting near Watchman 132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Daer Wind Farm 132/33kV: 96 MW waiting
- Rivox 132/33kV: 220 MW waiting
- Glenglass 132/33kV: 60 MW waiting
- ELVANFOOT ENERGY STORAGE 132/33KV COLLECTOR SUBSTATION: 75 MW waiting
- Elvanfoot substation: 44 MW waiting