Ceislien Wind Farm: grid connection queue
Ceislien Wind Farm · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 86 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 31 Oct 2030 to 31 Oct 2030.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Ceislein Wind Farm | RWE Renewables UK Onshore Wind Limited | Onshore wind | 86 | 31 Oct 2030 | High | 16 Sep 2032 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 0 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 13 Oct 2026 | Ceislein Wind Farm | 31 Oct 2031 | 31 Oct 2030 | -12 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Dingwall Primary | SSEN Distribution | 1.5 km | 0 MW | 0 MW |
| Conon Bridge Primary | SSEN Distribution | 3.4 km | 0 MW | 0 MW |
| Marybank Primary | SSEN Distribution | 9.9 km | 0 MW | 0 MW |
| Muirend Primary | SSEN Distribution | 10.3 km | 0 MW | 0.1 MW |
| Muir of Ord Primary | SSEN Distribution | 10.6 km | 0 MW | 0 MW |
| Orrin GSP | SSEN Distribution | 12.5 km |
Thinking of connecting near Ceislien Wind Farm?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Fyrish 132kV: 200 MW waiting
- Fyrish 275kV: 170 MW waiting
- Fairburn Extension 132/33kV: 90 MW waiting
- Orrin: 101 MW waiting
- BEAULY 02 BESS 132kV SUBSTATION: 100 MW waiting