Fyrish 132kV: grid connection queue
Fyrish 132kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 200 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2029 to 31 Oct 2029.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Fyrish Battery Storage | Field Fyrish Ltd | Battery storage | 200 | 31 Oct 2029 | Medium | 31 Oct 2029 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Contullich Primary | SSEN Distribution | 3.2 km | 0 MW | 0.1 MW |
| Alness GSP | SSEN Distribution | 4.0 km | ||
| Crosshills Primary | SSEN Distribution | 4.7 km | 0 MW | 4 MW |
| Invergordon Primary | SSEN Distribution | 10.0 km | 0 MW | 5 MW |
| Dingwall Primary | SSEN Distribution | 12.1 km | 0 MW | 0 MW |
| Blackstand Primary | SSEN Distribution | 14.7 km | 0 MW | 4.1 MW |
Thinking of connecting near Fyrish 132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Fyrish 275kV: 170 MW waiting
- Creachan Wind Farm 132/33kV: 79 MW waiting
- Strathy South 132/33kV: 208 MW waiting
- Alness 2 275/33 kV GSP: 95 MW waiting
- Alness: 43 MW waiting