Creachan Wind Farm 132/33kV: grid connection queue

Creachan Wind Farm 132/33kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026

1 project with 79 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 31 Oct 2030 to 31 Oct 2030.

1project in the queue
79 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
79 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Creachan Wind FarmRWE Renewables UK Onshore Wind LimitedOnshore wind7931 Oct 2030High16 Sep 2032Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Crosshills PrimarySSEN Distribution0.9 km0 MW4 MW
Alness GSPSSEN Distribution2.1 km
Contullich PrimarySSEN Distribution2.5 km0 MW0.1 MW
Invergordon PrimarySSEN Distribution4.7 km0 MW5 MW
Peddieston PrimarySSEN Distribution10.0 km0 MW1.6 MW
Blackstand PrimarySSEN Distribution11.5 km0 MW4.1 MW

Thinking of connecting near Creachan Wind Farm 132/33kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points