Mybster 3 132/33kV: grid connection queue
Mybster 3 132/33kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026
2 projects with 117 MW are waiting to connect here (largest by capacity: solar + storage, battery storage). Contracted dates run from 30 Jun 2028 to 30 Jul 2028.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Tormsdale Windfarm | ASUK HOLDCO 1 LIMITED | Solar + storage | 70 | 30 Jun 2028 | High | 30 Jun 2030 | Scoping | none |
| Lisa's Battery Storage | POTENCIA ENERGY LIMITED | Battery storage | 47 | 30 Jul 2028 | High | 30 Jul 2030 | Consents Approved | 2 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 18 Aug 2026 | Tormsdale Windfarm | 30 Jun 2027 | 30 Jun 2028 | +12 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Latheron Primary | SSEN Distribution | 7.4 km | 0 MW | 1.1 MW |
| Dunbeath GSP | SSEN Distribution | 10.4 km | ||
| Mybster 1 GSP | SSEN Distribution | 11.3 km | ||
| Mybster 2 GSP | SSEN Distribution | 11.3 km | ||
| Wick Primary | SSEN Distribution | 18.2 km | 0 MW | 5 MW |
| Halkirk Primary | SSEN Distribution | 18.6 km | 0 MW | 0 MW |
Thinking of connecting near Mybster 3 132/33kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Mybster 2 132/33kV: 86 MW waiting
- Mybster 4 132/33kV GSP: 40 MW waiting
- Spittal 2 400kV: 1,000 MW waiting
- Spittal 400kV: 600 MW waiting
- Spittal 132kV: 462 MW waiting