Mybster 3 132/33kV: grid connection queue

Mybster 3 132/33kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026

2 projects with 117 MW are waiting to connect here (largest by capacity: solar + storage, battery storage). Contracted dates run from 30 Jun 2028 to 30 Jul 2028.

2projects in the queue
117 MWwaiting to connect
0 MWalready connected
47 MWholding Gate 2
1date moves since 2 Jun 2026
117 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Tormsdale WindfarmASUK HOLDCO 1 LIMITEDSolar + storage7030 Jun 2028High30 Jun 2030Scopingnone
Lisa's Battery StoragePOTENCIA ENERGY LIMITEDBattery storage4730 Jul 2028High30 Jul 2030Consents Approved2

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
18 Aug 2026Tormsdale Windfarm30 Jun 202730 Jun 2028+12 months

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Latheron PrimarySSEN Distribution7.4 km0 MW1.1 MW
Dunbeath GSPSSEN Distribution10.4 km
Mybster 1 GSPSSEN Distribution11.3 km
Mybster 2 GSPSSEN Distribution11.3 km
Wick PrimarySSEN Distribution18.2 km0 MW5 MW
Halkirk PrimarySSEN Distribution18.6 km0 MW0 MW

Thinking of connecting near Mybster 3 132/33kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.